- High-rise developments in the GTA currently average 11 years to complete, while low-rise projects take 10 years.
- Historical data shows a significant gap between housing approvals and completions, with ratios in complex regions dropping to 60%–70%.
- Industry group BILD identifies shifting municipal policies, new taxes, and changing building requirements as primary risks to project viability.
Why it matters · our take
Protracted approval timelines and policy instability increase financial risks for developers, often leading to stalled projects and a persistent shortfall in housing supply despite high paper approval numbers.
This is a short AI-generated summary. For the complete reporting, photos, and full context, please read the original article at the publisher.
Read full article at Toronto Sun - HomesRelated Stories
- Storeys · BC
Choice Properties REIT Buys Royal Oak Wholesale Club In Burnaby For $38.5M
- REM Online · Ontario
Falcomer: Earning your commission when your buyer has AI
- REM Online · Ontario
People don’t want to be sold: What Peggy Hill knows about earning trust in a difficult market
- Toronto Star - Real Estate · Ontario
Developer at centre of secret Muskoka land deal with province changes course on waterfront project